BAL rating and BAL assessment: what the levels mean

Updated RapidSiteplan

A BAL rating, short for bushfire attack level, is the grade of bushfire attack a building has to be designed for, and a BAL assessment is how that grade is worked out for one site. There are six levels, from BAL-LOW to BAL-FZ, the flame zone, as per AS 3959, and the rating for a site comes from the vegetation near it, the slope of the land under that vegetation and the distance between them.

To check one block, type its address into RapidSiteplan: it reads the lot and the rules that apply there and checks the structure you place against them, in minutes.

What do the bushfire attack levels mean?

LevelWhat the site facesWhat it asks of the building
BAL-LOWToo little risk to set requirementsNo bushfire construction requirements
BAL-12.5Ember attack, with low radiant heatSealed gaps, screened vents and openings, and materials embers will not catch
BAL-19More ember attack, burning debris and rising radiant heatThe same list, with tougher materials and glazing
BAL-29Ember attack, burning debris and higher radiant heatRequirements that tighten hard on walls, windows, decks and roofs
BAL-40Radiant heat high enough that flames may reach the buildingConstruction close to the strictest, with tested window and door systems
BAL-FZThe flame zone: direct contact with the fire frontThe strictest construction in AS 3959, and in some states a limit on new homes

The rating belongs to the site, not the suburb. Bushfire-prone does not mean a fire is coming. It means the land sits where bushfire attack is possible, and buildings there have to be designed to survive it.

What does BAL-12.5 mean?

BAL-12.5 is the first level that brings construction requirements. It is set for ember attack with low radiant heat, so the work starts with sealing gaps, screening vents and openings, and choosing materials that embers will not catch. BAL-19 adds to the same list, and from BAL-29 the requirements tighten hard.

What is a BAL assessment?

A BAL assessment works out the level for one building site. The assessor maps the vegetation within reach of the site, measures the slope under it and the distance to the building, and reads the level from the method in AS 3959. A bushfire consultant does it, or for simpler sites the certifier, and the result decides how the building is built. Where the site is close to a level’s edge, moving the building further from the vegetation can bring it down a level, so the assessment belongs before the design settles.

Where is the bushfire prone land map?

The levels are national, but every state draws its own map of where they apply, under its own name, and the name matters when you search for it.

StateWhat the map is calledWhat it brings
QueenslandBushfire prone area, mapped in each council’s planning scheme, usually as a bushfire hazard overlayA BAL for a new house, an addition or an attached structure, and the overlay’s own planning questions
New South WalesBush fire prone land, mapped for each council and certified by the state’s fire serviceA BAL for the building, and an assessment of the development for bush fire protection
VictoriaBushfire prone area for building, and a bushfire management overlay for planningA BAL for the building, and a planning permit where the overlay applies
South AustraliaBushfire hazard overlays in the state’s planning codeConstruction to the level the overlay and the site call for
Western AustraliaBush fire prone areas, designated on a state mapA BAL for the building, and a bushfire assessment for planning
TasmaniaBushfire-prone areas in the planning schemeA BAL for the building, and a bushfire hazard management plan where one is needed
ACTThe territory’s bushfire prone area mapBushfire construction for buildings inside it
Northern TerritoryAsk the certifier whether a mapped area applies to the lotBushfire construction where it does

RapidSiteplan shades the mapping over your real lot and warns you when a proposed structure lands in a mapped area, before the design settles, and the bushfire prone check reads it for an address.

Does a BAL assessment work differently in Queensland?

The method is the same, since the standard is national; what differs is the map that triggers it. In Queensland the trigger is the bushfire prone area in the council’s planning scheme, usually drawn as a bushfire hazard overlay, and the certifier asks for the level for a new house, an addition or an attached structure on that land. The Queensland page covers how the council and the certifier split the work.

Does a patio, deck or shed need a BAL assessment?

Often, on mapped land. Attached structures and anything near the house can change the dwelling's exposure, and a timber deck against a wall is the classic trigger. Expect your certifier to ask for a BAL assessment, and expect the material and detailing requirements to follow whatever rating comes back.

What is the flame zone?

The flame zone, BAL-FZ, is the top of the scale: a site close enough to the vegetation that flames can reach the building. Construction there is the strictest the standard sets, and planning rules in some states limit new homes at that level.

What only your address can answer

  • whether the lot is inside the mapped bushfire-prone area
  • the vegetation around the site, the slope of the land, and how far apart they are
  • the rating the building has to be designed for, which an assessment of the site sets
  • whether a planning overlay adds bushfire requirements of its own

RapidSiteplan reads your block from its address: the boundaries, the buildings already on it, the rules that apply there and any overlay or easement, and checks what you plan to build against them on a scaled site plan.

Search your address to start. Site plans and assessments in minutes.

Common questions

What does a BAL rating mean? A BAL rating, short for bushfire attack level, is the grade of bushfire attack a building has to be designed for. The six levels are BAL-LOW, BAL-12.5, BAL-19, BAL-29, BAL-40 and BAL-FZ, the flame zone, and the higher the level, the stricter the construction as per AS 3959.

What does BAL-12.5 mean? BAL-12.5 is the first level that brings construction requirements, set for ember attack with low radiant heat. Sealing gaps, screening vents and openings and choosing materials that embers will not catch are where it starts, and the assessment confirms the level for the site.

What is a BAL assessment? A BAL assessment works out the bushfire attack level for a building site from the vegetation around it, the slope of the land and the distance between them. A bushfire consultant or, for simpler sites, the certifier does it, and the result sets how the building has to be built.

Do I need a BAL assessment in Queensland? On land the council’s planning scheme maps as a bushfire prone area, yes: the certifier needs the level for a new house, an addition or an attached structure there. The method is the same as in the other states, because the standard is national.

What is the flame zone? The flame zone, BAL-FZ, is the top of the scale: a site close enough to the vegetation that flames can reach the building. Construction there is the strictest the standard sets, and planning rules in some states limit new homes at that level.

Where is the bushfire prone land map? Each state publishes its own, under its own name, and many councils carry it as an overlay in the planning scheme. RapidSiteplan shades the mapping over your lot and warns you when a proposed structure lands in a mapped area.

Read next

What is a wind classification?Why the supplier asks for your wind class first Does a carport need a BAL rating?On bushfire prone land a carport attached to the house, or close to it, is usually built to the house’s bushfire level Is a pergola exempt development in NSW?A pergola in New South Wales can be exempt development when it stays inside the state’s standards

General information only, not building or legal advice, requirements vary by council and change over time; always confirm with your council or certifier.

Monthly: what changed in council rules

One email a month, unsubscribe in one click.

Cookies and local storage

Essential cookies and local storage keep you signed in and hold your plan. Google Analytics and Microsoft Clarity measure how these public pages are used while you are signed out; untick Analytics to switch them off. No advertising, nothing sold.